Public projects

Costs, progress and cost changes of major infrastructure projects and IT projects, from the official dashboards.

Infrastructure projects of $20 million or more

Dashboard edition of 8 October 2026. Each project is compared with its first published cost since 19 May 2020: 69 editions are kept.

Projects tracked649including 266 under way
Total cost of costed projects$60.6B353 projects have a published cost
Cost change of costed projects+9.5%From $55.4B at first published cost to $60.6B in the latest edition. Construction inflation removed: −7.0%.

Sources: Secrétariat du Conseil du trésor, Dashboard of infrastructure projects of $20 million or more, dataset updated 8 October 2026; Statistics Canada, GDP (36-10-0222-01), construction prices (18-10-0289-01) and population of health regions (17-10-0157-01), dataset updated 24 July 2026.

Largest cost increases since the first published cost

Difference between the cost in the latest edition and the first published cost for the same project. The second view removes construction inflation: the first cost is brought to the latest edition's dollars with Québec's non-residential building construction price index.

Display
  • Tunnel Louis-Hippolyte-La Fontaine entre Montréal et Longueuil – Réfectionfrom $1.4B to $2.8B
    +$1.4B
  • Hôpital de l'Enfant-Jésus, complexe hospitalier – Québec – Construction et réaménagementfrom $2.0B to $2.7B
    +$689.4M
  • Hôpital de Lachine, complexe hospitalier – Montréal – Agrandissement et réaménagementfrom $95.0M to $367.8M
    +$272.8M
  • Hôpital Fleurimont, centre mère-enfant et service d'urgence – Sherbrooke – Constructionfrom $197.7M to $432.5M
    +$234.8M
  • Centre de transport Bellechasse de la STM – Montréal – Constructionfrom $370.3M to $584.5M
    +$214.2M
  • Route 389 (A) entre Fire Lake et Fermont – Reconstructionfrom $280.2M to $493.5M
    +$213.3M
  • Chemin de fer Québec Central entre Vallée-Jonction et Thetford Mines – Réfection et reconstructionfrom $440.3M to $640.7M
    +$200.4M
  • Édifice Gérard-D.-Levesque – Québec – Réfection et réaménagementfrom $184.4M to $340.0M
    +$155.6M
  • Hôpital Pierre-Le Gardeur, unités de soins – Terrebonne – Construction et agrandissementfrom $549.6M to $702.8M
    +$153.2M
  • École secondaire Louis-Philippe-Paré du centre de services scolaire des Grandes-Seigneuries – Châteauguay – Reconstruction et agrandissementfrom $343.6M to $467.8M
    +$124.2M
  • Hôpital de Verdun, unités de soins et soins ambulatoires – Montréal – Agrandissement et réaménagementfrom $264.9M to $385.2M
    +$120.3M
  • Autoroute 15 (des Laurentides), direction nord, entre Boisbriand et Mirabel, voie réservée – Aménagementfrom $191.7M to $292.1M
    +$100.4M
  • Réseau de télécommunications par fibre optique – Nunavik – Constructionfrom $160.6M to $257.9M
    +$97.3M
  • Route Billy-Diamond (route de la Baie-James) (phase I) – Nord-du-Québec – Réfectionfrom $264.7M to $348.2M
    +$83.5M
  • Hôpital général juif (Phase IV) – Montréal – Réaménagement et agrandissementfrom $269.9M to $345.9M
    +$76.0M
  • Tunnel Louis-Hippolyte-La Fontaine entre Montréal et Longueuil – Réfectionfrom $2.1B (2026 dollars) to $2.8B
    +$726.9M
  • Hôpital de Lachine, complexe hospitalier – Montréal – Agrandissement et réaménagementfrom $140.2M (2026 dollars) to $367.8M
    +$227.6M
  • Chemin de fer Québec Central entre Vallée-Jonction et Thetford Mines – Réfection et reconstructionfrom $496.4M (2026 dollars) to $640.7M
    +$144.3M
  • Hôpital Fleurimont, centre mère-enfant et service d'urgence – Sherbrooke – Constructionfrom $291.8M (2026 dollars) to $432.5M
    +$140.7M
  • Route 389 (A) entre Fire Lake et Fermont – Reconstructionfrom $371.8M (2026 dollars) to $493.5M
    +$121.7M
  • Édifice Gérard-D.-Levesque – Québec – Réfection et réaménagementfrom $220.9M (2026 dollars) to $340.0M
    +$119.1M
  • Centre de transport Bellechasse de la STM – Montréal – Constructionfrom $503.8M (2026 dollars) to $584.5M
    +$80.7M
  • Réseau de télécommunications par fibre optique – Nunavik – Constructionfrom $178.2M (2026 dollars) to $257.9M
    +$79.7M
  • Autoroute 15 (des Laurentides), direction nord, entre Boisbriand et Mirabel, voie réservée – Aménagementfrom $239.3M (2026 dollars) to $292.1M
    +$52.8M
  • Hôpital Pierre-Le Gardeur, unités de soins – Terrebonne – Construction et agrandissementfrom $658.4M (2026 dollars) to $702.8M
    +$44.4M
  • Musée national de l'histoire du Québec – Québec – Réfection et réaménagementfrom $62.0M (2026 dollars) to $105.0M
    +$43.0M
  • Musée de l'Holocauste – Montréal – Constructionfrom $68.8M (2026 dollars) to $110.0M
    +$41.2M
  • Palais de justice de Rouyn-Noranda – Constructionfrom $115.6M (2026 dollars) to $154.1M
    +$38.5M
  • Centre sportif et communautaire – Mont-Royal – Constructionfrom $43.7M (2026 dollars) to $80.5M
    +$36.8M
  • Maison des aînés et alternative spécialisée (ancien CHSLD) – Macamic – Agrandissement et réaménagementfrom $88.4M (2026 dollars) to $124.5M
    +$36.1M
View the data
Infrastructure project cost increases, edition of 8 October 2026
ProjectSectorStatusFirst cost published onFirst published costCurrent costIncreaseIncrease (%)First cost, in latest edition dollarsIncrease, inflation removedIncrease, inflation removed (%)Expected completion
Tunnel Louis-Hippolyte-La Fontaine entre Montréal et Longueuil – RéfectionRéseau routierEn réalisation2020-10-26$1.4B$2.8B$1.4B+96.1%$2.1B$726.9M+35.1%Août 2027
Hôpital de l'Enfant-Jésus, complexe hospitalier – Québec – Construction et réaménagementSanté et Services sociauxEn réalisation2020-05-19$2.0B$2.7B$689.4M+35.0%$2.9B−$246.9M−8.5%Décembre 2031
Hôpital de Lachine, complexe hospitalier – Montréal – Agrandissement et réaménagementSanté et Services sociauxEn réalisation2020-05-19$95.0M$367.8M$272.8M+287.2%$140.2M$227.6M+162.3%Septembre 2028
Hôpital Fleurimont, centre mère-enfant et service d'urgence – Sherbrooke – ConstructionSanté et Services sociauxEn service2020-05-19$197.7M$432.5M$234.8M+118.8%$291.8M$140.7M+48.2%Juillet 2025
Centre de transport Bellechasse de la STM – Montréal – ConstructionTransport collectifEn réalisation2021-06-07$370.3M$584.5M$214.2M+57.8%$503.8M$80.7M+16.0%Septembre 2026
Route 389 (A) entre Fire Lake et Fermont – ReconstructionRéseau routierEn réalisation2021-07-26$280.2M$493.5M$213.3M+76.1%$371.8M$121.7M+32.7%Novembre 2028
Chemin de fer Québec Central entre Vallée-Jonction et Thetford Mines – Réfection et reconstructionTransports maritime, aérien, ferroviaire et autresEn réalisation2023-09-28$440.3M$640.7M$200.4M+45.5%$496.4M$144.3M+29.1%Août 2028
Édifice Gérard-D.-Levesque – Québec – Réfection et réaménagementAdministration gouvernementaleEn réalisation2022-06-02$184.4M$340.0M$155.6M+84.4%$220.9M$119.1M+53.9%Avril 2027
Hôpital Pierre-Le Gardeur, unités de soins – Terrebonne – Construction et agrandissementSanté et Services sociauxEn réalisation2022-05-25$549.6M$702.8M$153.2M+27.9%$658.4M$44.4M+6.8%Juillet 2029
École secondaire Louis-Philippe-Paré du centre de services scolaire des Grandes-Seigneuries – Châteauguay – Reconstruction et agrandissementÉducationEn réalisation2021-05-27$343.6M$467.8M$124.2M+36.1%$467.5M$305,769+0.1%Octobre 2027
Hôpital de Verdun, unités de soins et soins ambulatoires – Montréal – Agrandissement et réaménagementSanté et Services sociauxEn réalisation2020-10-26$264.9M$385.2M$120.3M+45.4%$384.4M$755,385+0.2%Juillet 2027
Autoroute 15 (des Laurentides), direction nord, entre Boisbriand et Mirabel, voie réservée – AménagementRéseau routierEn réalisation2022-03-22$191.7M$292.1M$100.4M+52.4%$239.3M$52.8M+22.1%Décembre 2027
Réseau de télécommunications par fibre optique – Nunavik – ConstructionDéveloppement du territoire nordique et des communautés autochtonesEn réalisation2024-03-12$160.6M$257.9M$97.3M+60.6%$178.2M$79.7M+44.7%Décembre 2027
Route Billy-Diamond (route de la Baie-James) (phase I) – Nord-du-Québec – RéfectionDéveloppement du territoire nordique et des communautés autochtonesEn réalisation2020-05-19$264.7M$348.2M$83.5M+31.5%$390.7M−$42.5M−10.9%Novembre 2026
Hôpital général juif (Phase IV) – Montréal – Réaménagement et agrandissementSanté et Services sociauxEn réalisation2022-12-08$269.9M$345.9M$76.0M+28.2%$313.4M$32.5M+10.4%Septembre 2030
Palais de justice de Rouyn-Noranda – ConstructionAdministration gouvernementaleEn réalisation2021-06-07$85.0M$154.1M$69.1M+81.3%$115.6M$38.5M+33.2%Septembre 2030
Palais de justice de Saint-Hyacinthe – Reconstruction et agrandissementAdministration gouvernementaleEn réalisation2021-06-07$122.0M$185.5M$63.5M+52.0%$166.0M$19.5M+11.8%Février 2027
Maison des aînés et alternative spécialisée (ancien CHSLD) – Macamic – Agrandissement et réaménagementSanté et services sociauxEn réalisation2021-06-07$65.0M$124.5M$59.5M+91.5%$88.4M$36.1M+40.8%Décembre 2026
Musée d'art contemporain de Montréal – Agrandissement et réaménagementCultureEn réalisation2020-05-19$57.0M$116.5M$59.5M+104.4%$84.1M$32.4M+38.5%Janvier 2028
Maison des aînés et alternative (ancien CHSLD) – Maniwaki – ConstructionSanté et services sociauxEn service2021-06-07$70.0M$127.4M$57.4M+82.0%$95.2M$32.2M+33.8%Juin 2025
Musée national de l'histoire du Québec – Québec – Réfection et réaménagementCultureEn service2022-03-22$49.7M$105.0M$55.3M+111.3%$62.0M$43.0M+69.3%Mars 2026
Hôpital Santa Cabrini, bloc opératoire – Montréal – Agrandissement et réaménagementSanté et Services sociauxEn réalisation2021-06-07$96.3M$151.2M$54.9M+57.0%$131.0M$20.2M+15.4%Avril 2026
Garage de la STL (phase IV) – Laval – ConstructionTransport collectifEn réalisation2022-03-22$247.2M$299.0M$51.8M+21.0%$308.5M−$9.5M−3.1%Décembre 2026
Centre sportif et communautaire – Mont-Royal – ConstructionDéveloppement du sportEn réalisation2020-11-16$30.1M$80.5M$50.4M+167.4%$43.7M$36.8M+84.3%Octobre 2028
École secondaire de Chambly du centre de services scolaire des Patriotes – Agrandissement et réaménagementÉducationEn réalisation2020-09-09$158.4M$207.3M$48.9M+30.9%$230.8M−$23.5M−10.2%Janvier 2027
Download the data (CSV)

Sources: Secrétariat du Conseil du trésor, Dashboard of infrastructure projects of $20 million or more, dataset updated 8 October 2026; Statistics Canada, GDP (36-10-0222-01), construction prices (18-10-0289-01) and population of health regions (17-10-0157-01), dataset updated 24 July 2026.

Cost history of a project

Cost published in each edition of the dashboard, in current dollars.

Source: Secrétariat du Conseil du trésor, Dashboard of infrastructure projects of $20 million or more, dataset updated 8 October 2026.

Infrastructure projects by region

Cost of projects of $20M or more under way or planned (not yet in service) that involve a single region. The 9 projects involving several regions ($6.9B) are not allocated. Click a region to see its projects.

Display
  • Nord-du-Québec12 projects · $1.6B
    $117,649
  • Côte-Nord11 projects · $1.8B
    $22,326
  • Capitale-Nationale33 projects · $8.1B
    $9,953
  • Montréal74 projects · $19.8B
    $8,994
  • Bas-Saint-Laurent4 projects · $1.2B
    $5,644
  • Saguenay–Lac-Saint-Jean9 projects · $1.5B
    $5,203
  • Montérégie32 projects · $6.3B
    $4,220
  • Abitibi-Témiscamingue9 projects · $559.4M
    $3,811
  • Chaudière-Appalaches7 projects · $1.6B
    $3,512
  • Centre-du-Québec7 projects · $854.6M
    $3,252
  • Lanaudière13 projects · $1.7B
    $3,107
  • Gaspésie–Îles-de-la-Madeleine5 projects · $231.8M
    $2,583
  • Laurentides12 projects · $1.7B
    $2,470
  • Laval9 projects · $710.2M
    $1,547
  • Outaouais10 projects · $605.4M
    $1,434
  • Mauricie7 projects · $324.2M
    $1,140
  • Estrie3 projects · $144.0M
    $275
  • Montréal74 projects · $19.8B
    $19.8B
  • Capitale-Nationale33 projects · $8.1B
    $8.1B
  • Montérégie32 projects · $6.3B
    $6.3B
  • Côte-Nord11 projects · $1.8B
    $1.8B
  • Lanaudière13 projects · $1.7B
    $1.7B
  • Laurentides12 projects · $1.7B
    $1.7B
  • Chaudière-Appalaches7 projects · $1.6B
    $1.6B
  • Nord-du-Québec12 projects · $1.6B
    $1.6B
  • Saguenay–Lac-Saint-Jean9 projects · $1.5B
    $1.5B
  • Bas-Saint-Laurent4 projects · $1.2B
    $1.2B
  • Centre-du-Québec7 projects · $854.6M
    $854.6M
  • Laval9 projects · $710.2M
    $710.2M
  • Outaouais10 projects · $605.4M
    $605.4M
  • Abitibi-Témiscamingue9 projects · $559.4M
    $559.4M
  • Mauricie7 projects · $324.2M
    $324.2M
  • Gaspésie–Îles-de-la-Madeleine5 projects · $231.8M
    $231.8M
  • Estrie3 projects · $144.0M
    $144.0M

Sources: Secrétariat du Conseil du trésor, Dashboard of infrastructure projects of $20 million or more, dataset updated 8 October 2026; Ministère des Affaires municipales et de l'Habitation, Financial profile and financial reports of municipalities, dataset updated 24 October 2026; Ministère des Ressources naturelles et des Forêts, Geographic and administrative database, administrative divisions at 1:5,000,000, Administrative divisions (regions and RCMs), version V2026-09, simplified for display, published September 2026.

Québec Infrastructure Plan 2026-2036, by sector

Planned investments over ten years: $167.0B.

  • Road network
    $35.7B
  • Health and social services
    $24.7B
  • Education
    $23.5B
  • Public transit
    $12.8B
  • Higher education
    $9.2B
  • Information resources
    $8.9B
  • Municipalities
    $7.3B
  • Marine, air, rail and other transportation
    $6.3B
  • Government administration
    $5.8B
  • Social and community housing
    $3.5B
  • Culture
    $2.7B
  • Tourism and recreation
    $1.6B
  • Environment
    $1.5B
  • Sport development
    $1.3B
  • Northern and Indigenous community development
    $1.3B
  • Research
    $1.3B
  • Agriculture, forests and wildlife
    $669.3M
  • Educational childcare
    $491.2M
  • Economic development
    $56.2M
  • Central envelope (not allocated)
    $18.0B
View the data
Québec Infrastructure Plan 2026-2036
SectorAmount
Road network$35.7B
Health and social services$24.7B
Education$23.5B
Public transit$12.8B
Higher education$9.2B
Information resources$8.9B
Municipalities$7.3B
Marine, air, rail and other transportation$6.3B
Government administration$5.8B
Social and community housing$3.5B
Culture$2.7B
Tourism and recreation$1.6B
Environment$1.5B
Sport development$1.3B
Northern and Indigenous community development$1.3B
Research$1.3B
Agriculture, forests and wildlife$669.3M
Educational childcare$491.2M
Economic development$56.2M
Central envelope (not allocated)$18.0B
Download the data (CSV)

Source: Secrétariat du Conseil du trésor, Québec Infrastructure Plan 2026-2036, p. A.21, summary of planned QIP 2026-2036 investments by sector, published 18 March 2026.

Information resources projects

Data collected in October 2026 for the dashboard on the health of public administration IT projects.

Active projects143out of 167 projects tracked
Estimated cost of active projects$2.1BAuthorized cost: $2.1B. Already spent: $1.0B.
Active projects with a red cost rating823 with a red schedule rating

Source: Ministère de la Cybersécurité et du Numérique, Health status of information resources projects, dataset updated 7 October 2026.

Largest overruns, active IT projects

Overrun: estimated cost minus authorized cost, two values published in the dashboard.

  • Projet Véo+175.2%
    +$64.0M
  • Programme de sélection des travailleurs qualifiés (PSTQ)+35.6%
    +$3.5M
  • Gestion de la représentation (volet privé)+9.8%
    +$3.3M
  • Évolution gestion des opérations aériennes (GOA)+108.4%
    +$1.9M
  • Délestage Notes - Demande de services inter-établissement (DSIE)+173.1%
    +$1.5M
  • Salles interrogatoire vidéo+35.0%
    +$1.2M
  • Outil de gestion des dépenses (EMT)+151.3%
    +$1.2M
  • Bonification du Régime de rentes du Québec - Volet 2+12.5%
    +$1.1M
  • Mise en place d'une solution logicielle pour la gestion de l'éthique des projets impliquant des humains+76.0%
    +$830,400
  • Refonte du SCAVAC+33.4%
    +$798,700
  • Solution gouvernementale de gestion des apprentissages – SGGA+7.7%
    +$754,800
  • Service bureautique gouvernemental _3_Modernisation de l'offre de service bureautique et outils de migration+1.7%
    +$605,400
  • HORIZON - Logistique+7.4%
    +$476,800
  • Gestion du dossier étudiant (GDE) (Programme SIGÉ)+3.5%
    +$367,700
  • 9-1-1 de prochaine génération (NG911)+8.0%
    +$317,400
View the data
Overruns of active IT projects, collected in October 2026
ProjectBodyAuthorized costEstimated costOverrunOverrun (%)ProgressCost ratingSchedule rating
Projet VéoUniversité de Sherbrooke$36.6M$100.6M$64.0M+175.2%—RedRed
Programme de sélection des travailleurs qualifiés (PSTQ)Ministère de l'Immigration, de la Francisation et de l'Intégration$9.8M$13.3M$3.5M+35.6%75.0%RedYellow
Gestion de la représentation (volet privé)Curateur public$33.9M$37.2M$3.3M+9.8%90.0%GreenGreen
Évolution gestion des opérations aériennes (GOA)Ministère des Transports et de la Mobilité durable$1.7M$3.6M$1.9M+108.4%—RedGreen
Délestage Notes - Demande de services inter-établissement (DSIE)Santé Québec$859,000$2.3M$1.5M+173.1%—RedRed
Salles interrogatoire vidéoSûreté du Québec$3.5M$4.8M$1.2M+35.0%—RedGreen
Outil de gestion des dépenses (EMT)Université McGill$812,300$2.0M$1.2M+151.3%—RedRed
Bonification du Régime de rentes du Québec - Volet 2Retraite Québec$8.9M$10.1M$1.1M+12.5%—YellowRed
Mise en place d'une solution logicielle pour la gestion de l'éthique des projets impliquant des humainsUniversité Laval$1.1M$1.9M$830,400+76.0%—RedYellow
Refonte du SCAVACMinistère de la Justice$2.4M$3.2M$798,700+33.4%—RedRed
Solution gouvernementale de gestion des apprentissages – SGGAMinistère de la Cybersécurité et du Numérique$9.8M$10.6M$754,800+7.7%—GreenYellow
Service bureautique gouvernemental _3_Modernisation de l'offre de service bureautique et outils de migrationMinistère de la Cybersécurité et du Numérique$35.1M$35.7M$605,400+1.7%17.0%GreenGreen
HORIZON - LogistiqueMinistère de la Sécurité intérieure$6.4M$6.9M$476,800+7.4%98.0%GreenYellow
Gestion du dossier étudiant (GDE) (Programme SIGÉ)Université du Québec à Montréal$10.5M$10.9M$367,700+3.5%2.0%GreenGreen
9-1-1 de prochaine génération (NG911)Ministère des Ressources naturelles et des Forêts$4.0M$4.3M$317,400+8.0%—GreenRed
Remplacement du CMS (Rhythmyx)École des hautes études commerciales de Montréal$2.4M$2.6M$234,300+9.9%—GreenYellow
Intégration des données sur le personnel des commissions scolairesMinistère de l'Éducation$4.2M$4.5M$230,000+5.4%—GreenRed
Optimisation des services de francisation et des plaintes (OSFTP) volet 2Office québécois de la langue française$3.8M$4.0M$206,200+5.5%40.0%GreenGreen
API Gateway (APIM)Agence du revenu du Québec$4.7M$4.9M$200,000+4.2%—GreenYellow
Accessibilité webTélé-université$1.1M$1.3M$181,300+16.7%—YellowGreen
Download the data (CSV)

Source: Ministère de la Cybersécurité et du Numérique, Health status of information resources projects, dataset updated 7 October 2026.

Active IT projects by portfolio

Estimated cost of active projects, with the number of projects and of projects with a red rating (cost or schedule).

  • Santé et Services sociaux14 projects, 5 red
    $881.4M
  • Cybersécurité et Numérique7 projects, 1 red
    $285.0M
  • Finances23 projects, 2 red
    $253.8M
  • Enseignement supérieur29 projects, 8 red
    $201.6M
  • Justice7 projects, 3 red
    $123.4M
  • Agriculture, Pêcheries et Alimentation4 projects, 0 red
    $69.7M
  • Sécurité intérieure6 projects, 1 red
    $48.8M
  • Immigration, Francisation et Intégration2 projects, 1 red
    $39.2M
  • Famille1 projects, 0 red
    $37.2M
  • Transports et Mobilité durable9 projects, 1 red
    $26.2M
  • Travail8 projects, 1 red
    $23.9M
  • Éducation5 projects, 2 red
    $16.2M
View the data
Active IT projects by portfolio, collected in October 2026
PortfolioProjectsEstimated costRed projects
Santé et Services sociaux14$881.4M5
Cybersécurité et Numérique7$285.0M1
Finances23$253.8M2
Enseignement supérieur29$201.6M8
Justice7$123.4M3
Agriculture, Pêcheries et Alimentation4$69.7M0
Sécurité intérieure6$48.8M1
Immigration, Francisation et Intégration2$39.2M1
Famille1$37.2M0
Transports et Mobilité durable9$26.2M1
Travail8$23.9M1
Éducation5$16.2M2
Culture et Communications6$16.1M0
Conseil du trésor et Administration gouvernementale2$10.9M0
Ressources naturelles et Forêts2$9.0M1
Environnement, Lutte contre les changements climatiques, Faune et Parcs4$8.0M1
Économie, Innovation et Énergie2$6.9M0
Conseil exécutif1$4.9M0
Tourisme5$4.2M0
Affaires municipales et Habitation5$4.2M0
Langue française1$4.0M0
Download the data (CSV)

Source: Ministère de la Cybersécurité et du Numérique, Health status of information resources projects, dataset updated 7 October 2026.